Dear Residents,
As you know the Parish Council has been working with Staffordshire County Council to ensure that the S106 funds for traffic calming are used to deliver an effective solution to the traffic through Bramshall Village.
Most of you will have commented on the first proposed chicane design/location and plans were redrawn after listening to residents concerns.
The second design/location went out for consultation and I am happy to say that the design will now be implemented having successfully passed through the consultation process.
You will have seen the drawing on our website in September (News Item)
The work on the chicane is due to start within the next month, so should be finished by Christmas 2019, this of course is weather permitting.
The drawings are below in a pdf format.
Thank you
Bramshall Chicane D6665T-R00-04-P1 – Consultation Drawing 17.09.2019